Serica Resumes Production from Bruce Platform

OE Staff
Monday, March 9, 2020

London-listed Serica Energy has resumed production from its Bruce platform in the UK sector of the North Sea, following a halt in January.

Production was halted on Bruce while engineering work was carried out to secure an unused caisson, which was found to be in a deteriorated condition. 

"The engineering work has been successfully completed and production has restarted. It is anticipated that production from the Bruce, Keith, and Rhum fields will be fully restored over the coming days," Serica said.

Mitch Flegg, Chief Executive of Serica Energy, commented: "We are delighted that we have been able to restart production considerably sooner than we had initially predicted.

"Our expert teams onshore and offshore have successfully executed a program of repairs during some of the most difficult weather conditions experienced in the North Sea for several years. Together with selected contractors we have completed these repairs safely and with no environmental impact."

"This work will have no negative impact on future production rates or on the ultimate recovery of reserves from Bruce, Keith, and Rhum."

Serica acquired interests in the Bruce, Keith, and Rhum (BKR) fields and associated offshore facilities from BP, Total, BHP, and Marubeni in November 2018.

<




 
Credit; Serica Energy

Categories: Energy Engineering Subsea North Sea Activity Oil Production Gas

Related Stories

81m Acres Opened in Gulf of America Lease Sale

CNOOC Commissions Phase I of Bozhong 19-6 Gas Field

ConocoPhillips Hires Noble Corporation’s Jack-Up for Ekofisk P&A Work

Current News

DOF Group Announces Subsea Contracts in the APAC Region

Russian Crude Production Falls Lower Amidst Global Uncertainty, Sanctions

TGS and GTI Collaborate on Seismic Acquisition

Tupi Sets Petrobras Production Record

Subscribe for OE Digital E‑News