First oil has started flowing from the BP-operated Alligin field in the West of Shetland region, offshore UK.

Alligin is a part of the Greater Schiehallion Area and has been developed as a two-well subsea tie-back into the existing Schiehallion and Loyal subsea infrastructure and the Glen Lyon FPSO unit.

The field is a 20-million-barrel of oil equivalent asset originally projected to produce 12,000 barrels gross of oil equivalent a day at peak. 

"The project’s performance has been better than expected, however, reaching 15,000 barrels gross of oil equivalent a day at peak since start-up in late December," BP said Tuesday.

The development 50-50 owned by Shell and BP has included new subsea infrastructure, consisting of gas lift and water injection pipeline systems, and new control umbilical. 

BP North Sea Regional President Ariel Flores said: “Achieving first oil from the Alligin field safely, under budget and ahead of schedule is testament to the performance of the project team and their agile approach to planning and execution.

 “Alligin is part of BP’s advantaged oil strategy, a development with a shorter project cycle time with oil that is economic to produce and low risk to bring to market. Subsea tiebacks like this complement our major start-ups and help underpin our growing portfolio west of Shetland. 

 

Categories: Subsea North Sea Europe Oil Production

Related Stories

Equinor, DNO Wrap Up Appraisal of Two Wells in Heisenberg Discovery

Nexans Secures First Call-Off Under TenneT’s Offshore Wind Grid Deal

Gondan Cuts First Steel for New USV for Major Industry Alliance

Current News

First Gas Export to Denmark from Tyra II Expected Today

Vattenfall to Take Part in IJmuiden Ver Offshore Wind Tender in Netherlands

Beach Energy to Let Go 30% of Workforce Amid Strategic Review

Ocean Infinity Inks Deal with Shell for Subsea Data Capture Services

Subscribe for OE Digital E‑News