Serica Halts BKR Production as Issues Found on Bruce Platform

OE Staff
Thursday, January 30, 2020
Bruce Platform - Image: Serica Energy

The North Sea operator Serica Energy has halted production from Bruce, Keith and Rhum (BKR) fields, after an inspection unveiled issues aboard the Bruce offshore platform.

"During a Bruce platform inspection, the condition of an unused seawater return caisson on the platform was observed to have deteriorated."

"This caisson had been taken out of service in 2009. Production through the Bruce facility was halted while the problem was fully investigated," Serica said on Thursday.

According to Serica, a subsequent underwater inspection determined that the unused caisson had parted below the waterline. 

"Both the upper and lower sections of the caisson are intact. Engineering work to ensure that the caisson is properly secured has commenced. Preliminary estimates are that this work will take approximately two months, following which production will be restored," Serica said.

Serica said: "During this period there will be no production from the Bruce, Keith, and Rhum fields. The financial impact is mitigated by the net cash flow sharing arrangements entered into by Serica with the sellers of interests in the fields in 2018."

Serica's other activities, including its share of production from the Erskine field, are unaffected.

Mitch Flegg, Chief Executive of Serica Energy, commented: "Although this is a frustrating event, our skilled offshore team have reacted very efficiently. The underwater investigation quickly determined the cause of the problem and a solution is being planned to allow the resumption of full production."

Serica acquired interests in the Bruce, Keith, and Rhum (BKR) fields and associated offshore facilities from BP, Total, BHP, and Marubeni in November 2018.

Categories: North Sea Industry News Activity Europe Production UKCS Subsea

Related Stories

DNO Inks Gas Offtake Deal with Engie, Secures $500M Financing Facility

DNO Inks Gas Offtake Deal with Engie, Secures $500M Financing Facility

Triton FPSO Set to Come Back Online with Full Ramp Up to Follow

Triton FPSO Set to Come Back Online with Full Ramp Up to Follow

Jotun FPSO Starts Production at Balder Field in North Sea

Jotun FPSO Starts Production at Balder Field in North Sea

Current News

Bonaparte CCS Project Awarded Major Project Status

Borr Drilling Announces CEO Succession Plan

One Shelf Drilling Rig Up for New Job in India, Other for Disposal

Semco Maritime Gets Iberdrola’s Baltic Hub Substations Service Job

Subscribe for OE Digital E‑News

Offshore Engineer Magazine