Petrofac Completes BorWin3 OWP

Laxman Pai
Wednesday, August 21, 2019

Petrofac, the provider of oilfield services to the international oil and gas industry, announced the start of power generation from a major offshore wind project (OWP) in Germany.

The 900 mega-watt BorWin3 platform has started the process of converting power from offshore windfarms and transmitting it to the country’s national grid about 100 miles away.

Petrofac, in consortium with Siemens, were awarded the BorWin3 offshore grid connection project contract in 2014 by TenneT, the German-Dutch transmission grid operator, with responsibility for the engineering, procurement, construction, transport and offshore installation of the platform offshore.

The jacket foundation was installed in May 2018, and the topside integrated in October 2018 following its sea voyage from Dubai where it was fabricated and the completion of a mammoth float-over installation procedure.

George Salibi, Chief Operating Officer – Engineering & Construction at Petrofac said: “We are delighted to have reached this key milestone with BorWin3 ready for action. The additional grid connection being put into operation is a significant contribution to the energy transition in Germany and a further demonstration of Petrofac’s expansion into adjacent sectors, including renewable energy.”

Categories: Wind Power Offshore Energy Renewable Energy Offshore Wind Renewables

Related Stories

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Cadeler’s WTIV Newbuild En Route to Europe for Maiden Offshore Wind Job

DNV Boosts Offshore Wind and Renewables Team

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Subscribe for OE Digital E‑News