UK-Denmark Subsea Power Cable Gig Awarded

Laxman Pai
Wednesday, July 24, 2019

The Italian electric power transmission specialists Prysmian, German multinational conglomerate Siemens and Swedish cable manufacturer have secured contracts worth a total 1.1 billion euros ($1.2 billion) to build the world’s longest subsea power cable, the Viking Link between Britain and Denmark.

National Grid and Energinet have recently announced that these cable and converter station suppliers are chosen for the UK’s first ever subsea electricity inter-connector to Denmark.

The 1.4 GW high voltage direct current inter-connector, which will be the longest in the world when completed, will stretch 768 kilometers from Lincolnshire to Western Denmark.

The project will consist of two parallel HVDC cables which will be manufactured and installed by Prysmian Powerlink S.r.l. and NKT HV Cables AB.

Industrial manufacturing company Siemens will be supplying and installing equipment for two converter station sites in Lincolnshire, UK and Revsing, Denmark.

The three contracts have a combined value of 1.1 billion Euros.

Viking Link will now move from development to the construction phase, with work in the UK and Denmark beginning next summer. Construction on Viking Link is expected to be completed by the end of 2023.

Categories: Transmission/Gears Subsea Subsea Cables Power Generation

Related Stories

XOCEAN Secures Five-Year Survey Deal for Six Dutch Offshore Wind Farms

NSTA Names 13 Operators Falling Behind Decom Obligations in North Sea

Subsea7 Hooks Decom Work with Ithaca Energy off UK

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Subscribe for OE Digital E‑News