Ivar Aasen Now Operated from Land

Thursday, January 17, 2019

Aker BP on Wednesday said it has begun operating the permanently manned North Sea platform Ivar Aasen from an onshore control room in Trondheim, Norway.

The Ivar Aasen platform was constructed with two identical control rooms – one on the platform and the other in Trondheim – and the Norwegian company said the plan has always been to move the controls to land. 

The company received the green light from Norway's Petroleum Safety Authority in November and this week started using its onshore site to monitor facilities, production, equipment and follow up everything that takes place on the field. The control room also plays a role in activating work permits, and for the arrival of vessels and helicopters within the 500-meter zone, it said.

Aker BP said even with controls moved to shore the staff of about 70 people working on Ivar Aasen, 175 kilometers off Norway's west coast, will remain as before.

The company admits there is still much to be learned from this new method of managing (both for Aker BP and for the industry), but said the activity unlocks considerable potential for increased revenues because subsurface experts are closer to the control room.

Categories: Technology Europe Production Automation

Related Stories

Exploration Well in Black Sea Offshore Block Comes Up Dry

50Hertz, Skyborn Ink Deal for Gennaker Offshore Converter Platforms

European North Sea Investment Pact to Mobilize $1.17T for Offshore Wind

Current News

Chevron Signs Oil Exploration Deal in Syrian Waters

Oil Companies Snap Up West African Blocks in Search for Next Big Thing

BOEM Advances Second OBBBA Offshore Lease Sales

Boskalis Subsea Services Launches Collective-Based Model for North Sea Decommissioning

Subscribe for OE Digital E‑News