The Petroleum Safety Authority Norway (PSA) have given Statoil consent to put the Gina Krog facility and associated pipeline system into service. 

In June 2016, Statoil received partial consent from the PSA to put into service the accommodation quarters, cranes, pipelines and other parts of the Gina Krog facility that were necessary for activities in the phase leading up to production start-up.

With consent from the PSA, Statoil can now put into service the facility's production plant and associated pipeline system, which comprises the gas export pipeline between Gina Krog and Sleipner A, the oil export pipeline between the Gina Krog facility and the Gina Krog FSO (floating storage and offloading) storage unit, and the gas import pipeline from Zeepipe IIA to Gina Krog. The consent also includes an installation for the future reception of power from onshore.

An application from Statoil to deploy the Gina Krog FSO facility is currently being processed by the PSA.

Categories: Installation Support Vessel Europe Engineering Pipelines Vessels

Related Stories

Jumbo Scoops Two Offshore Wind Contracts

ABB’s Streamlined DP2 System Passes Sea Trials on DEME’s Norse Wind WTIV

ESG Completes Service Operation Vessel Conversion for HOS

Current News

BOEM Initiates Process for Potential Mineral Lease Sale Offshore Virginia

Jumbo Scoops Two Offshore Wind Contracts

Wood Nets Long-Term Maintenance Contract for Rio Grande LNG Facility

TechnipFMC to Supply Subsea Systems for Chevron’s Gas Project off Australia

Subscribe for OE Digital E‑News