KBR, SOCAR in Absheron FEED

OE Staff
Thursday, November 23, 2017

Azerbaijan's SOCAR and US engineering house KBR's joint venture has been awarded a front end engineering and design (FEED) contract for topsides on Total's Absheron Early Production Project.

The platform will be at SOCAR's Oil Rocks facility and will deliver gas and condensate into the SOCAR network. 

Last November, Total and national oil company SOCAR, agreed on terms for a first phase of production of the high-pressure Absheron gas and condensate field, which was discovered in the Caspian Sea by Total in 2011. 

At the first stage, the field development includes drilling one well at a depth of 450m. The extraction will amount to 1.5 Bcm of gas a year, or 35,000 boe/d, as well as significant amounts of condensate. First gas could be produced as early as 2019. 

This first phase of production will also enable a dynamic appraisal of the field for future phases. Total is the operator of Absheron with a 40% interest alongside SOCAR (40%) and ENGIE (20%).

The contract is the joint venture's third award since its inception in mid-2015. 

 
Categories: Middle East

Related Stories

ADES Lands $48M Nigeria Contract for Main Pass IV Rig

ADNOC Drilling Posts Record First-Quarter Results with 5% Revenue Rise

Gulf Marine Services Profit Plunges After Gulf Vessel Evacuations

Current News

Seraya Partners Considers Sale, IPO for Offshore Wind Firm Cyan Renewables

ScioSense Launches UFC23 Ultrasonic Flow Converter for High-Precision, Ultra-Low-Power Smart Metering

All Systems Go for Technip Energies' Job at Commonwealth LNG Scheme

Ocean Winds Gets Full Onshore Approval for Caledonia OW Project

Subscribe for OE Digital E‑News