Lukoil starts Filanovsky drilling

OE Staff
Thursday, December 7, 2017

Lukoil has started drilling the first production well at the Vladimir Filanovsky field after completing construction of the field’s second phase development facilities.

The company plans to complete drilling early next year, Lukoil said in a 7 December statement. The phase two facilities will allow field production to reach a plateau of 6MM tonnes/year.

Production from the field’s first phase, which includes six production wells and two injection wells, has surpassed 5MM tonnes per oil.

Located in the Russian sector of the Caspian Sea, Filanovsky started operations in 2016. The field, which is being developed in three phases, holds initial recoverable reserves of 129MM tonnes of oil and 30 Bcm of gas.

Phase 1 includes a fixed ice resistant platform, an accommodation block platform, a riser block and a central processing platform. Eight wells have been drilled in this phase. Phase 2 facilities include a fixed ice resistant platform and an accommodation block platform. Construction of the field’s third development phase, a wellhead platform, started this year.

Read more:

Eighth well on Vladimir Filanovsky drilled

Bumi bags Lukoil EPCI in Caspian

Lukoil's Phase 2 Filanovsky topsides set sail

Categories: Russia

Related Stories

Brazil Pushes Out Petrobras CEO, Names Ex-Regulator to Top Job

Vard Selects TMC to Equip Prysmian’s Newbuild Cable Laying Vessel

Valaris Jack-up Using AI for Man Overboard Detection

Current News

Pertamina and ExxonMobil Plan Appraisal Drilling in Carbon Capture Effort

STARS: The Missing Link in Deep Sea Mining Supply Chain

Orbital Marine and GEG Ink Tidal Energy Preferred Supplier Agreement

Føn Energy Services and C-Ventus Enter Offshore Wind Merger

Subscribe for OE Digital E‑News