First Steel Cut for Karish and Tanin FPSO

Tuesday, November 27, 2018

Energean Oil and Gas announced that first steel was cut on the Karish and Tanin floating production storage and offloading (FPSO) vessel at the COSCO yard in Zhoushan, China, on Monday. The FPSO is scheduled to be delivered to the Karish field offshore Israel in late 2020, ahead of first production in the first quarter of 2021.

The FPSO, which will be installed 90 kilometers offshore, will be the first FPSO to operate in the Eastern Mediterranean. It will have a gas treatment capacity of 800 MMscf/day (8 BCM/per annum) and liquids storage capacity of 800,000 bbls.

Energean, an E&P company with operations offshore Israel, Greece and the Adriatic, has contracted TechnipFMC under a turnkey, lump sum EPCIC contract to deliver the FPSO and SURF for the development of the Karish & Tanin project with first gas planned for Q1 2021.

Energean is planning to spud in March 2019 Karish North, the first of four wells planned to be drilled in Israel during 2019. Karish North is targeting 1.3 TCF of prospective resources with a very high chance of success over and above the 2.4Tcf 2P reserves in Karish-Tanin. Energean has already signed firm contracts for 4.2 bcma of gas sales into the Israeli domestic market. Future gas sales agreements will focus on both the growing Israeli domestic market and key export markets in the region.

Mathios Rigas, CEO of Energean said, “The cutting of the first steel on the Karish-Tanin FPSO marks an important and symbolic moment for our flagship Karish -Tanin project and for Energean as a whole. I would like to thank the tireless work that has gone into getting us to this moment and look forward to hitting our milestones to first production in 1Q 2021, contributing to security and diversity of supply in the Israeli markets as well as giving Energean the optionality to target key regional export markets. We have gone from asset acquisition to FID in 15 months and to cutting first steel in under two years.”

Energean Israel owns 100 percent and is the operator of the Karish and Tanin leases, offshore Israel. The fields have 2.2 TCF of natural gas and 31.8 million barrels of light hydrocarbon liquids independently audited 2P reserves plus 5.4 BCM of gas and 1.0 mmbls of liquids 2C resources. NSAI has audited 2.94 TCF of gas plus 78.8 mmbls of liquids unrisked prospective resources.

Energean made Final Investment Decision for the development project in March 2018, after having signed 12 Gas Sales and Purchase Agreements for 4,2 BCM in total annually and secured financing for the project.

The Karish main field will be the first asset to be developed in the Karish and Tanin blocks. Karish is the largest discovery, is expected to provide the highest yield of liquid per volume of produced gas and is the closest discovery to shore. Capex for the Karish development (First Phase) is estimated at $1.6 billion.

Categories: Shipbuilding Offshore Vessels Middle East Offshore Energy FPSO Floating Production Construction

Related Stories

Subsea Vessel Market is Full Steam Ahead

DEME Scoops ‘Most Extensive’ Cabling Contract in Its History

DEME’s Orion Vessel Heads to US After Finishing Scottish Offshore Wind Job

Current News

Talos Energy Makes Leadership Team Changes

SOVs – Analyzing Current, Future Demand Drivers

Equinor Cleared for Drilling Ops at Johan Castberg Field with Transocean Enabler Rig

Skanska Set for South Brooklyn Marine Terminal Buildout

Subscribe for OE Digital E‑News