Deutsche Bucht Offshore Wind Substation Nears Completion

Posted by Michelle Howard
Wednesday, November 21, 2018

Ten months after the final assembly of the offshore substation (OSS) for the new Deutsche Bucht offshore wind farm started at Damen Shiprepair Vlissingen (DSV), the substation topside has now been moved outside the construction hall so that further outfitting can take place.

The Deutsche Bucht offshore wind farm, owned by Northland Power, will have 33 turbines, situated 95 kilometers northwest of Germany’s Borkum Island, in the North Sea. The wind farm will have a total capacity of 269 MW.

Van Oord is managing the overall Balance of Plant scope, including the OSS project, with the joint venture Iemants-Eiffage contracted for the engineering, procurement, construction and installation of the substation topside and jacket. Together with Damen Schelde Naval Shipbuilding, DSV is managing the yard facilities and supporting the OSS works by providing welding and painting services.

Offshore installation is planned in the first half of 2019.

Categories: Offshore Wind Power Renewable Energy Engineering Europe Construction Renewables

Related Stories

CBED Signs Up Siemens Gamesa for Wind Creation SOV’s First Job

Allseas Makes Progress on Santos’ Barossa Gas Export Pipeline in Australia

COWI to Design Foundations for GW-Scale Irish Offshore Wind Project

Current News

US Plans 12 Offshore Wind Auctions Over Five Years

Equinor Wraps Up Hammerfest LNG Leak Repair, Maintains Friday Restart

Namibia Targets First Oil Production from Venus Field in 2029/2030

Second HVDC Platform Installed at World’s Largest Offshore Wind Farm

Subscribe for OE Digital E‑News