Deutsche Bucht Offshore Wind Substation Nears Completion

Posted by Michelle Howard
Wednesday, November 21, 2018

Ten months after the final assembly of the offshore substation (OSS) for the new Deutsche Bucht offshore wind farm started at Damen Shiprepair Vlissingen (DSV), the substation topside has now been moved outside the construction hall so that further outfitting can take place.

The Deutsche Bucht offshore wind farm, owned by Northland Power, will have 33 turbines, situated 95 kilometers northwest of Germany’s Borkum Island, in the North Sea. The wind farm will have a total capacity of 269 MW.

Van Oord is managing the overall Balance of Plant scope, including the OSS project, with the joint venture Iemants-Eiffage contracted for the engineering, procurement, construction and installation of the substation topside and jacket. Together with Damen Schelde Naval Shipbuilding, DSV is managing the yard facilities and supporting the OSS works by providing welding and painting services.

Offshore installation is planned in the first half of 2019.

Categories: Offshore Wind Power Engineering Renewable Energy Europe Construction Renewables

Related Stories

Bibby Marine’s Battery-First eCSOV Hits Water in Spain

MacGregor to Equip IWS’ Four Skywalker-Class CSOV Newbuilds

DOF Nears Large Contract for I-Class Vessel

Current News

Equatorial Guinea Aseng Project on Track for First Gas Delivery in 2028

Guardian to Lead Bullwinkle Platform Decommissioning in US Gulf

Sunda Energy Gains Exclusive Status for New Zealand Offshore Permit Bid

DOF Inks Extension Deal for Skandi Nomad Subsea Vessel

Subscribe for OE Digital E‑News