Offshore Wind: Fugro Starts Site Survey in the Baltic

Posted by Michelle Howard
Friday, September 14, 2018

Fugro has commenced a marine site characterization program at Iberdrola’s Baltic Eagle Offshore Wind Farm, in German waters of the Baltic Sea.

Under a contract worth over €10 million ($11 million), Fugro will undertake a UXO survey to clear the investigation sites, followed by a geotechnical seabed investigation and borehole drilling. The workscope also includes a program of standard and advanced laboratory testing.

The fieldwork takes place between August 2018 and February 2019 from Fugro vessels including the geophysical vessel Fugro Pioneer and geotechnical drilling vessel, Fugro Scout. To enhance quality and bring operational efficiency to the project, Fugro will deploy the proven Geobor-S piggy back drilling system, and its team of geophysical, geological and geotechnical experts will complement and optimize the final deliverables.

The data will inform the design of the foundations for the wind turbines and offshore substation, which will be installed in water depths of up to 45 meters.

With a total capacity of up to 476 megawatts and spanning an area of 35 square kilometers, the Baltic Eagle wind farm is located 30 kilometers off the coast of the German island of Rügen.

Categories: Contracts Wind Power Geoscience Subsea Underwater Engineering Hydrographic Offshore Energy Renewable Energy Surveyors Offshore

Related Stories

Cydome Rolls Out Remote Cybersecurity Tool for Offshore Wind Farms

TGS Embarks on Multi-Client 2D Survey off Angola

HydroWing Wins 10MW CfD Boost for Morlais Tidal Energy Project

Current News

Ndungu Full-Field Starts Up Offshore Angola

Norway's 2025 Oil Output Climbs to Highest Level Since 2009

AKOFS Offshore Inks New Vessel Deal with Petrobras

UK Trade Body Challenges Government View on North Sea Gas Decline

Subscribe for OE Digital E‑News