Aker BP, a partner in Norway's giant Johan Sverdrup oilfield, expects a fast ramp-up of production when the initial development phase ends in late 2019, its chief executive said on Thursday.

"I think it will be done in a few months, because the production per well is so high," Karl Johnny Hersvik told Reuters on the sidelines of an energy conference.

Johan Sverdrup Phase 1 will have capacity to produce 440,000 barrels of oil equivalents per day (boed), while the second phase, starting production in 2022, is expected to further boost output to 660,000 boed.

Sweden's Lundin Petroleum, another partner in the Equinor-operated, on Wednesday said it expected the field to start producing before November next year.

Equinor has said it expects the field to start in late 2019 but has not provided an estimate for when the first phase could reach full capacity.


(Reporting by Nerijus Adomaitis, editing by Terje Solsvik)

Categories: Offshore Offshore Energy Energy

Related Stories

Van Oord Completes Monopile Installation at Windanker

Australian Union Members Back Pluto LNG 2 Strike

Fugro Wraps Up Survey at Dogger Bank South Offshore Wind Farm

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Subscribe for OE Digital E‑News