Tennet Relocates Submarine Cable from Borssele

The transmission system operator Tennet has moved the first submarine cable from the Dutch wind farm zone "Borssele" to the transformer station.

"TenneT has laid the first sea cable to connect the Alpha platform to the transformer substation in Borssele. In the morning of Friday 12 April, VBNK started withdrawing the sea cable on land and early Saturday morning the cable reached the newly built transformer substation," said a press release.

The cable-laying vessel, Giant 7, then repositioned itself in the Honte and started with the most critical part of the installation: crossing the fairway.

Before crossing the channel, shipping traffic to and from the port of Antwerp was blocked until Sunday afternoon. The crossing went completely according to plan and the traffic got back on track in the course of the evening.

In the coming weeks, preparations will be made to also connect the second sea cable for the Borssele Alpha project to the transformer station.

Current News

Driven by Oil & Gas, Norway Wealth Fund Approachs $2 Trillion

Driven by Oil & Gas, Norway We

OPEC+ Passes on Oil Output Increase, Weighs the "Trump Effect"

OPEC+ Passes on Oil Output Inc

Petrobras Slashes Platform Decommissioning Budget

Petrobras Slashes Platform Dec

NOIA Reacts as BOEM Announces Next Steps for GoM Oil & Gas

NOIA Reacts as BOEM Announces

Subscribe for OE Digital E‑News

Offshore Engineer Magazine