Tanks installed on Caribbean FLNG project

Wison Offshore & Marine Ltd. (WOM) successfully completed the installation of the three LNG storage tanks into the hull of the Caribbean FLNG project. The project’s barge deck and topsides will now be installed.

The Caribbean FLNG project, supplied to EXMAR by Wison under an EPCIC contract, will be installed offshore Colombia.  The project started fabrication at the end of 2012 and is planned to be in operation the first quarter of 2015 as the world’s first FLNG vessel. The project is progressing on schedule and is expected to be completed in April 2014.

The combined capacity of the three LNG storage tanks, which were supplied by TGE, is 16,100cu m, with a net weight of approximately 395 tons each. The complete tanks were hoisted by two 400-ton goliath gantry cranes in WOM’s dry dock.

Current News

Trump Administration to Cancel Approval of Maryland Offshore Wind Project

Trump Administration to Cancel

Trump's Halt of Rhode Island Wind Project Stuns Local Leaders

Trump's Halt of Rhode Island W

Luxcara Reserves Siemens Gamesa Turbines After Setting Deal with Ming Yang Smart Energy

Luxcara Reserves Siemens Games

AMIGO LNG Signs 15-Year LNG Sale and Purchase Agreement with Macquarie Group

AMIGO LNG Signs 15-Year LNG Sa

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine