Petrofac awards HFG platform fabrication contract

Published

Petrofac has awarded Heerema Fabrication Group (HFG) an AFC contract to fabricate the substation platform for Galloper Wind Farm (GWFL).

Heerema Hartlepool is fabricating the unmanned offshore substation platform. Project engineering and procurement are being undertaken by Petrofac as part of the GE Petrofac Consortium. 

The Galloper Offshore Wind Farm is an extension to the Greater Gabbard Wind Farm, but is being developed as an entirely separate entity. In 2008, the Greater Gabbard topsides transformer platform was Heerema Hartlepool’s first EPC project in the offshore wind energy sector.

The Galloper substation platform will connect turbine generators to a single offshore substation platform (OSP) by subsea array cables. The OSP will be linked to the onshore transition joint bay near Sizewell by two subsea export cables. The offshore site is located within the outer Thames Estuary, 27km off the Suffolk coast with water depths of 27-39m. 

Sail away of the platform is scheduled early in 2017.

Image: Signing the Galloper contract/Heerema Fabrication Group

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

Dajin Forms Offshore Wind Alli

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

EnerMech Hires Former SLB Exec

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Eni Expands Asian Footprint wi

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Jasmund Substation’s Topside a

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine