Eni targets OCTP gas by 2018

Published

Italy's Eni announced that its gas development offshore Cape Three Points (OCTP), Ghana, is 63% complete, with start-up planned for 2018.

Eni said that construction on the onshore receiving facility and associated pipelines are proceeding as planned. Gas produced by OCTP will allow Ghana to generate a minimum of 900 MW, which might, in the future, increase to up to 1500 MW.

Eni achieved first oil from OCTP back in May 2017, three months ahead of schedule. Eni expects to ramp up production to 5.2 MMbbl from the 2.8 MMbbl initially expected. The project is expected to reach a plateau of 45,000 bo/d by end of 2017.

The project comprises the Sankofa Main, Sankofa East and Gye-Nyame fields, about 60km off Ghana. It was completed in 29 months. The fields, which contain about 770 MMboe in place, including 500 MMbo and 270 MMboe (41 Bcm) of non-associated gas, are being produced via the John Agyekum Kufuor floating production, storage and offloading unit (FPSO).

The OCTP project includes Eni (44.44% and operator), Vitol (35.56%), and GNPC [Ghana National Petroleum Corp.] (20%).

Read more

Eni starts OCTP production early

Current News

Orbital Marine Power Secures $9.31m Investment

Orbital Marine Power Secures $

Shell Seeks Buyer for 20% Stake in Brazilian Oilfield Cluster

Shell Seeks Buyer for 20% Stak

VAALCO Energy Spuds First Well in New Drilling Campaign off Gabon

VAALCO Energy Spuds First Well

US Judge Overturns Trump’s Freeze on Wind Energy Permits

US Judge Overturns Trump’s Fre

Subscribe for OE Digital E‑News

 
Offshore Engineer Magazine