First Gas Achieved on BW Opal FPSO

Sunday, September 21, 2025

BW Offshore’s BW Opal FPSO has achieved First Gas on September 20, after successfully reaching Ready for Start-Up (RFSU) for the Santos operated Barossa LNG project on September 16, initiating 60% of the contractual dayrate under the charter.

First Gas represents a critical juncture in the formal transition from project to operations phase and demonstrates BW Opal’s readiness to deliver stable energy production.

The next milestone, Interim Performance Test (IPT), will increase the payable dayrate to 85%. The final milestone, Practical Completion (PC), will conclude the delivery phase, trigger 100% of the dayrate, and mark the commencement of the 15-year firm contract period, securing long-term revenues for the Company under the charter agreement.

The BW Opal FPSO, designed to process 850 million standard cubic feet per day (MMSCFD) of gas and capacity of 11,000 barrels per day of stabilized condensate, will operate in the Santos operated Barossa gas field, located 285 kilometers offshore Darwin in the Northern Territory of Australia.

Categories: Offshore FPSO Production Oil and Gas Australia Well Operations Workover

Related Stories

Aker Solutions Widens Work Scope for BP into Central North Sea

Unity Launches Compact BOP for Constrained Wells

Expro Picks Up 14-Well Life-Extension Campaign off Canada

Current News

Aker BP Names New Executive Management Team

Eco Atlantic’s Namibia Farm-Down to BP Clears Final Approval

DOF Nears Large Contract for I-Class Vessel

New Owner to Extend Life of Germany’s First Offshore Wind Farm

Subscribe for OE Digital E‑News