Beacon Offshore Energy Begins Production US at Shenandoah Field

Friday, July 25, 2025

Beacon Offshore Energy LLC said it began oil and natural gas production at its Shenandoah field off the coast of Louisiana on Friday, nearly a month after it was originally expected to commence.

Beacon, which in May said it expects first oil in June, expects to ramp up the Phase 1 wells during the third quarter to deliver about 100,000 barrels per day (bpd).

The floating production system has a nameplate capacity of 120,000 bpd and 140 million cubic feet per day.

Phase 2 of the Shenandoah development is expected to be drilled and completed by mid-2026.

The Houston-based privately held company also sanctioned the development of the Shenandoah South project, with initial production from the first well expected to occur in the second quarter of 2028.

(Reuters)

Categories: Industry News Activity Production Offshore Oil & gas Oil Production Shale LNG Renewables Inspection & Repair & Maintenance ROV & Dive Support Construction Vessel

Related Stories

Petrobras Nears Deal With SBM Offshore for Two Sergipe FPSOs

Orlen Looks for Partner for 1GW Polish Offshore Wind Project

Mexican Billionaire Slim Calls Pemex's Lakach Project “Irrational”

Current News

SBM Offshore Wins Contracts for SEAP-I and SEAP-II FPSOs

Decommissioning: IMCA Issued Diver Safety Guide

Engineering for Extremes (II): Accuracy & Efficiency in Offshore Drilling

TotalEnergies Makes Middle East Oil Trades After US Navy Buildup in Gulf

Subscribe for OE Digital E‑News