TenneT Completes Onshore Works to Link Three Dutch Offshore Wind Farms to Grid

Tuesday, December 17, 2024

TenneT has completed the onshore work scope required to connect three offshore wind farms to the Dutch grid -  Hollandse Kust (noord), (west Alpha) and (west Beta).

The project has been completed four years after the first underground drilling from the Westerhout estate in Beverwijk.

The electricity cables have been installed at an average depth of 30 meters from sixteen work sites in Heemskerk, Beverwijk and Velsen.



As part of the work, the transformer station on Zeestraat in Wijk aan Zee has also been built where the export cables will be connected.

“In 2025, we will install the superstructure of the offshore socket on the base that is already 53 kilometers off the coast of Egmond aan Zee. We will then test the cable connection and the various systems,” said project director Jaap Nijland on behalf of TenneT.

The third and final connection will be ready at the end of 2025, after which operator RWE will be able to connect the Oranjewind wind farm to the national high-voltage grid.

Categories: Renewable Energy Industry News Activity Europe Grid Offshore Wind

Related Stories

Akita Offshore Wind Build Progresses as JERA Defies Cost Pressures

NOV’s GustoMSC to Design Korea’s Wind Turbine Installation Vessel

UK Grants Consent for 1.5GW Outer Dowsing Offshore Wind Farm

Current News

Ndungu Full-Field Starts Up Offshore Angola

Norway's 2025 Oil Output Climbs to Highest Level Since 2009

AKOFS Offshore Inks New Vessel Deal with Petrobras

UK Trade Body Challenges Government View on North Sea Gas Decline

Subscribe for OE Digital E‑News