Equinor's Hammerfest LNG Plant Offline after Outage

Terje Solsvik and Nora Buli
Friday, May 5, 2023

Equinor's Hammerfest LNG plant in Arctic Norway suffered a compressor failure on Thursday and is expected to remain offline until May 19, Norwegian gas system company Gassco said in a regulatory note on Friday. 

The outage was caused by a technical problem with a heat exchanger that occurred during a restart of the plant following a one-day maintenance outage, an Equinor spokesperson said. 

The plant will remain offline until repairs have been carried out, the spokesperson added. Hammerfest LNG, also known as Melkoeya, has capacity to deliver about 6.5 billion cubic metres (bcm) of gas per year, enough to cover energy demand for about 6.5 million European homes, or 5% of all Norwegian gas exports, Equinor has said. 

Norway is Europe's largest supplier of natural gas following a sharp reduction in Russian deliveries amid the war in Ukraine. 

The Melkoeya plant receives its gas via a pipeline from the offshore Snoehvit gas field and is owned by operator Equinor (36.79%) as well as Petoro (30%), TotalEnergies TTEF.PA (18.40%), Neptune Energy (12%) and Wintershall Dea (2.81%). 

(Reuters - Reporting by Terje Solsvik and Nora Buli; Editing David Goodman and Jan Harvey)

Categories: Energy LNG Coastal/Inland Industry News Activity Europe Production Barents Sea

Related Stories

ESVAGT Acquires Two SOVs from Edda Wind

Subsea7 Answers Chevron’s Call for Work at Gas Field off Australia

Oil and Gas Redevelopment Project off Norway Gets $1.8B Approval

Current News

Shell Greenlights Waterflood Project to Bolster Production in Gulf of America

ESVAGT Acquires Two SOVs from Edda Wind

Dräger to Supply Gas Detection, Monitoring Tech to North Sea Operator

NKT Expands Swedish Cable Accessories Plant Amid Rising Demand

Subscribe for OE Digital E‑News