UK Allows Centrica to Reopen Rough Gas Storage Facility

Paul Sandle
Wednesday, August 31, 2022

Centrica's Rough gas storage site off England's east coast has received all the regulatory approvals to start storing gas again, Britain's oil and gas regulator said on Tuesday.

Countries across Europe have been building gas stocks ahead of winter to prepare for disruptions to supply of Russian gas, but Britain has had very little storage capacity since Rough's closure in 2018.

Britain's North Sea Transition Authority (NSTA) said it had granted the required approvals and consents to Centrica Offshore UK Limited for Phase 1 of the Rough gas storage site.

Centrica's Chief Executive Chris O'Shea said last month the company was carrying out the necessary engineering work to enable the site to reopen. 

It would be prepared to invest 2 billion pounds ($2.33 billion) in the project, he said.

The Rough site previously provided about 70% of Britain's gas storage capacity. 

Had the site been open last winter, it could have saved households about 100 pounds on their annual energy bills, O'Shea said last month.

 ($1 = 0.8576 pound)


 (Reuters - Reporting by Paul Sandle; editing by Jonathan Oatis)

Categories: Energy Industry News Activity Europe UKCS

Related Stories

GHL Seeks to Settle Dolphin Drilling Dispute with Cash, Nigeria Rig Work

Jan De Nul Enters CCS Market with North Sea Project

Well-Safe Solutions, NMC Energy Form Strategic Decom Partnership

Current News

CM Energy to Introduce CM Zenith Offshore Vessel to European Market in 2028

Milei Vows Tougher Sanctions, Defense Push Over Falklands Oil Drilling

ABS to Support Floating Offshore Wind Development in Brazil

Proserv Secures Equinor Contract for Dudgeon Offshore Wind Farm

Subscribe for OE Digital E‑News