Taqa Cleared to Remove Eider Platform Topside

Wednesday, May 27, 2020

The UK authorities have approved Taqa's decommissioning program the Eider platform topside in the UK North Sea

The Eider platform is located in Block 211/16a in the UK Northern North Sea. The field was discovered in May 1976 by Shell / Esso with the facility installed in June 1988 and production starting in November 1988. 

A Cessation of Production application for Eider was submitted in 2016 and accepted by the Oil and Gas Authority (OGA) in 2017, with production stopping in January 2018.  

The platform is located in 157.5 meters water depth and consists of a four-legged, eight-column steel jacket structure, weighing 11,606 Te.

Taqa has said it has carried out a review of the Eider asset to determine the feasibility of asset reuse. 

"The alternatives for reuse included: an offshore renewable energy generation station (wind, wave or tidal), a marine research station, a training center, fish farming site, carbon capture and storage site, and reuse of the facilities at an alternative location."

"However, after a thorough review TAQA concluded that reuse was not a credible option because of the age of the infrastructure, its
distance from shore and lack of demand for the converted facility. Therefore, the asset must be decommissioned," Taqa said.

This decommissioning work for the Eider topside envisions 2022 as the earliest possible date through to project completion in 2028.

Currently, the Eider platform is being retained as a low-cost utilities facility providing power generation back up to the North Cormorant
platform via a two-way power cable and subsea controls/utilities for the Otter field.

Taqa plans to use a semi-submersible crane vessel for the removal of the topside. The company has yet to decide whether to remove the topside as a complete unit in a single lift, or part by part.

Separate Decommissioning Programmes covering the remainder of the Eider substructure, currently planned for submission in 2020, associated pipelines, power cables, umbilicals and the Otter field tie back are currently planned for 2020+.

 

Categories: North Sea Industry News Activity Decommissioning

Related Stories

Fugro Gets Dogger Bank South Offshore Wind Survey Job

Mocean Energy’s Blue X Wave Device and Verlume’s Halo Battery Come Ashore

EnQuest Selling Stake in North Sea Golden Eagle Oil Field

Current News

Talos Energy Makes Leadership Team Changes

SOVs – Analyzing Current, Future Demand Drivers

Equinor Cleared for Drilling Ops at Johan Castberg Field with Transocean Enabler Rig

Skanska Set for South Brooklyn Marine Terminal Buildout

Subscribe for OE Digital E‑News