Equinor to Shut Hammerfest LNG Plant for Two Weeks in May

Nerijus Adomaitis
Wednesday, May 6, 2020

Equinor will shut down its Melkoyea liquefied natural gas (LNG) plant for two weeks of maintenance in the second half of May, the Norwegian oil and gas company said on Wednesday.

The shutdown of the plant, also called Hammerfest LNG, which liquefies natural gas from Equinor's Arctic Snoehvit field for export to the global market by tankers, will reduce production by 18 million cubic metres per day.

The company said the maintenance was a planned event, but it also comes at a time when demand is depressed amid coronavirus-related lockdown.

Equinor has a 36.8% stake in the Snoehvit field and the LNG plant. Its partners are Petoro with 30%, Total with 18.4%, Neptune Energy with 12% and Wintershall Dea with 2.8%. 

(Reporting by Nerijus Adomaitis, editing by Terje Solsvik)

Categories: Energy LNG Activity Arctic Inspection & Repair & Maintenance Barents Sea

Related Stories

Texas LNG Signs 20-Year Offtake Deal with Macquarie

Chevron's Gorgon LNG Project Gets $2B Investment Go-Ahead

Kongsberg Maritime Secures LARS Contract with Sea1 Offshore

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Subscribe for OE Digital E‑News