Russia's Lukoil said on Friday it had completed the construction of the first well as part of a third development stage of the V. Filanovsky oilfield in the Caspian Sea.

The well was drilled with a floating jack up rig Neptune, mounted on a riser block platform.

The newly constructed well has two bores and features TAML level 5 intelligent completion system. The drill depth of the main bore is 3,235 meters. The bottom of the side track is 3,261 meters deep. Planned daily flow rate of oil is 1,838 metric tons.

Produced oil is delivered to the Phase 1 central processing platform via a subsea pipeline. Phase 3, intended to maintain annual oil production at the planned production level of six million metric tons of oil, will integrate western part of the V. Filanovsky field in the development. Operation of the riser block platform is almost automatic and requires minimum involvement of the personnel.

Continuing operational drilling at Phase 1, the company has sidetracked two existing wells.

Categories: Drilling Activity Production

Related Stories

Oil Firms in Norway to Drill 18% Less Exploration Wells by 2026, Survey Finds

Vår Energi Makes Oil Find Near Goliat Field in Barents Sea

ADES Nets $63M Contract for Compact Driller Jack-Up off Brunei

Current News

Brazil’s Petrobras Targets Rapid Start-Up at Sudoeste de Tartaruga Verde

Jan De Nul Unveils ‘Most Advanced’ Wind Farm Installation Simulator

IWS Fleet Fills Charter Gaps, Secures New CSOV Deals Into 2028

Chevron Eyes New Nigeria Oil Blocks Aiming for Late-2026 Rig Arrival

Subscribe for OE Digital E‑News