Albatros Topside Installed

Wednesday, March 27, 2019

The topside of the offshore substation at the Albatros wind farm offshore Germany was installed Tuesday evening, developer EnBW said.

The heavy-lift jack-up vessel (HLJV) Pacific Ospray had loaded the topside in Rotterda, and once in the construction area, the HLJV Innovation lifted the topside on the foundation (monopile and transition piece) that had already been installed. 

The Pacific Ospray will be jacked up and remain next to substation until outstanding coating and welding work is completed.

Afterwards, the jack-up vessel Seafox2 will come to commission the offshore substation.

Categories: Engineering Activity Europe Renewables Installation

Related Stories

Cadeler, Vattenfall Team Up New Offshore Wind O&M Solutions

Aker BP Makes Gas Discovery in North Sea

RWE, Masdar Plan German Offshore Wind Partnership

Current News

Oil Drops as Hormuz Reopening Prospects Ease Supply Concerns

Strohm’s TCP Completes Qualification for Brazil’s Deepwater Pilot

ONGC Strikes Gas in Deepwater Well off India

PTTEP, Valeura Greenlight Bussabong Gas Development off Thailand

Subscribe for OE Digital E‑News