Swan Wraps Up Norther Offshore Cabling

Laxman Pai
Wednesday, March 6, 2019

Swan Hunter has completed work to spool export cables into storage baskets for the 370MW Norther offshore wind farm at its yard in Vlissingen, the Netherlands.

The UK-based shipbuilding design, engineering, and management company said in a press release that the last sections of spare array and export cables were transpooled from the Van Oord CLV Nexus, and the DOC-Swan Hunter 4750Te onshore basket carousel, to long term modular storage baskets.

The completion of this final spooling operation marks the end of a year long contract for Van Oord, which included export cable load-in from HLV Da Ji, interim storage and protection, export cable load-out to CLV Nexus, spare cable transpooling and handling operations, and finally transportation of the loaded baskets to the long term storage site in Belgium.

 “The successful completion of this project for Van Oord further exhibits our Storage and Spooling Yard as an attractive and strategic choice for installation contractors in the offshore wind industry," stated Director, Gerard Kroese.

He added: "With a busy yard schedule ahead for Q2 2019, the combination of our dedicated cable handling equipment and strategically placed ‘direct to sea’ yard, proves the attraction of our full service solution to the offshore wind industry supply chain”

Categories: Wind Power Subsea Cables Cabling Offshore Wind

Related Stories

Ignitis Places Bid for Second 700MW Lithuanian Offshore Wind Tender

Japan and US Team Up to Cut Floating Wind Costs

Venterra’s GDG to Provide Geophysical Services for Polish Offshore Wind Farm

Current News

Equinor's Hammerfest LNG Plant Evacuated Due to Gas Leak

Mocean Energy’s Blue X Wave Device and Verlume’s Halo Battery Come Ashore

Fugro’s Self-Elevating Platform On Call for Japan’s Offshore Wind

Galp Seeks to Sell Stake in Namibia Oilfield After Discovery

Subscribe for OE Digital E‑News