Seadrill agrees rig delivery deferment

OE Staff
Friday, January 15, 2016

Seadrill has reached an agreement with Daewoo Shipbuilding & Marine Engineering shipyard in South Korea to defer the delivery of two ultra-deepwater drillships, the West Aquila and West Libra, until Q2 2018 and Q1 2019 respectively.

Under the terms of the original construction contracts, the units were to be delivered by the end Q2 2016 and the total final yard installment for both units of over US$800 million was due at that time.  

This agreement significantly improves the company's near term liquidity position by deferring these capex commitments to 2018 and 2019 with no further payments to the yard until that time.

Categories: Rigs

Related Stories

Cydome Rolls Out Remote Cybersecurity Tool for Offshore Wind Farms

Fugro Starts Site Surveys for SSEN’s Western Isles Power Link

MacGregor Nets AHC Subsea Crane for Floating Wind Farm Vessel

Current News

Digital Threatscape is Rapidly Evolving for Global Energy Systems

Martens en Van Oord Purchases Autonomous Survey Vessel From Demcon unmanned systems

Mubadala Hires SLB for Deepwater Drilling Services Offshore Indonesia

Cydome Rolls Out Remote Cybersecurity Tool for Offshore Wind Farms

Subscribe for OE Digital E‑News