GAS gets Chirag survey gig

OE Staff
Monday, February 29, 2016

Italian geotechnical firm GAS has been appointed to perform survey and positioning support activities for the Chirag oil project offshore Azerbaijan. 

The work scope covers the laying of 8.33km of the 18in water injection pipeline and installation of tie-in spools in the Azeri Chirag and Gunashli (ACG) fields in the Caspian Sea, about 120km south east of capital Baku.

GAS will carry out pipelay support, prelay survey, as-laid survey, as-built survey and spools metrology.

The project will start in March 2016 and will take about four months.

The work was awarded as part of a frame agreement with Italian contractor Saipem. 

Categories: Gas

Related Stories

TotalEnergies’ Unit to Build Battery Storage Site in Japan to Help Balance Grid

TotalEnergies’ Unit to Build Battery Storage Site in Japan to Help Balance Grid

Israel Orders Energean to Halt FPSO Production as Iran Launches Counterstrikes

Israel Orders Energean to Halt FPSO Production as Iran Launches Counterstrikes

Topsides for Cenovus Energy’s West White Rose Platform En Route to Canada

Topsides for Cenovus Energy’s West White Rose Platform En Route to Canada

Current News

Commodity Report: Meeting Oil Demand a Challenge if Israel Hits Iran Oil

Egypt Halts Fertilizer Production In Light of Israeli Gas Disruptions

Edda Wind Welcomes New CSOV to its Fleet

TotalEnergies’ Unit to Build Battery Storage Site in Japan to Help Balance Grid

Subscribe for OE Digital E‑News

Offshore Engineer Magazine