HHI to keep delayed rig, reimburse Fred. Olsen

OE Staff
Monday, August 22, 2016

Bollsta Dolphin, Fred. Olsen Energy and Hyundai Heavy Industries have resolved their dispute and differences relating to the newbuilding contract for the semisubmersible drilling rig Bollsta Dolphin.

Ownership of the platform will be retained by HHI. Bollsta will receive about US$176 million from HHI, representing a reimbursement to Fred. Olsen of its initial payment for the rig. 

In a joint statement, the parties said: "We are very pleased that our differences have been resolved in an amicable way.”

The Bollsta Dolphin, ordered in 2012, had been due to be delivered in 2015, when it would start a five-year contract with Chevron. 

But, in October 2015, Fred Olsen said there was not realistic prospect of completion before May 2016 and cancelled the contract.

Bollsta Dolphin is a Moss Maritime CS 60 E design and is designed for water depth capacity up to 10,000ft.

Categories: HHI Construction Rigs Fabrication

Related Stories

TDI-Brooks Completes Offshore Seismic, Geochemical Surveys

ONGC Completes 44 Offshore Rig Moves Ahead of Monsoon Season

TotalEnergies Looks to Prioritize in Gulf Pipelines That Will Bypass Hormuz

Current News

TDI-Brooks Completes Offshore Seismic, Geochemical Surveys

Is Hindsight 20/20? Hormuz Oil Shock and Lessons Learned from 1973

Equinor Scuttles Japanese Offshore Wind Plan

Aker Solutions Inks 'Sizeable' Service Agreement

Subscribe for OE Digital E‑News