Siem axes PSV order due to delays

OE Staff
Wednesday, January 18, 2017

Siem Offshore has canceled the fourth of four dual fueled platform supply vessels (PSVs) shipbuilding-contracts with Remontowa Shipbuilding in Poland, due to delay in the delivery.

“The company is covered with refund guarantees from an international bank for all pre-delivery installments made under the contract,” says Siem Offshore. 

In December 2016, Siem canceled the third of the four PSV order for the same reason. 

The four vessels were ordered in December 2013, and were scheduled to be delivered from Q3 2015 to Q2 2016. 

Categories: Vessels Activity Europe

Related Stories

Heerema Completes Installation of First Hornsea 3 Offshore Converter Station

Cadeler Raises Over $200M to Fund Fleet Expansion Plans

DOF Gets Subsea Cable Replacement Job by Norway’s Statnett

Current News

Valaris Nets $447M Brazil Drillship Extension, Inks Suriname Collaboration Deal

SLB Expands Digital Operations Partnership with Azule Energy off Angola

France Sets Forth 10GW Offshore Wind Tender in Larger Renewables Push

Seadrill’s West Polaris Drillship on Prolonged Stay with Petrobras off Brazil

Subscribe for OE Digital E‑News