Siem axes PSV order due to delays

OE Staff
Wednesday, January 18, 2017

Siem Offshore has canceled the fourth of four dual fueled platform supply vessels (PSVs) shipbuilding-contracts with Remontowa Shipbuilding in Poland, due to delay in the delivery.

“The company is covered with refund guarantees from an international bank for all pre-delivery installments made under the contract,” says Siem Offshore. 

In December 2016, Siem canceled the third of the four PSV order for the same reason. 

The four vessels were ordered in December 2013, and were scheduled to be delivered from Q3 2015 to Q2 2016. 

Categories: Vessels Activity Europe

Related Stories

Van Oord Launches Giant Offshore Wind Installation Vessel

Brunvoll System to Propel Cyan Renewables New SOV

Cadeler Secures Up to $140M in Vessel Agreements with Equinor and Polenergia

Current News

Women in Maritime Day: Shaping the Future of Maritime Safety

New Dutch Coalition Aims for More Offshore Gas Extraction

Iberdrola to Triple Offshore Wind Assets

ABS Wavesight eLog Books for Offshore Drilling

Subscribe for OE Digital E‑News