Siem axes PSV order due to delays

OE Staff
Wednesday, January 18, 2017

Siem Offshore has canceled the fourth of four dual fueled platform supply vessels (PSVs) shipbuilding-contracts with Remontowa Shipbuilding in Poland, due to delay in the delivery.

“The company is covered with refund guarantees from an international bank for all pre-delivery installments made under the contract,” says Siem Offshore. 

In December 2016, Siem canceled the third of the four PSV order for the same reason. 

The four vessels were ordered in December 2013, and were scheduled to be delivered from Q3 2015 to Q2 2016. 

Categories: Vessels Activity Europe

Related Stories

CM Energy to Supply Cable Lay Equipment for Asso.subsea Vessel

Cadeler's Wind Apex WTIV Set for First Assignment at Dogger Bank C

Stillstrom Builds Vessel-Mounted System for Direct Offshore Wind Charging

Current News

Meyer Werft Establishes Organizational, Legal Framework for Offshore Converter Business

CM Energy to Supply Cable Lay Equipment for Asso.subsea Vessel

Sub-Saharan Africa: The Majors’ Next Wave of Growth

Worley Lands EPC Contract for Venture Global's CP2 LNG Expansion

Subscribe for OE Digital E‑News