Boskalis Installs All Foundations for Taiwan's Changfang & Xidao Offshore Wind Farm

Monday, July 17, 2023

Dutch marine services firm Boskalis said Monday it had completed the installation of all foundations for the 589 MW Changfang & Xidao offshore wind farm in Taiwan. 

"In the last three years we installed 186 pin piles with our unique crane vessels Bokalift 1 and Bokalift 2 and placed the 62 three-legged jacket foundations on top of them, literally providing Taiwan with a new horizon enabling our client, Changfang & Xidao, to provide clean and renewable energy for 650,000 Taiwanese households," Boskalis said. Credit: Boskalis 

After the first two campaigns, this year the Bokalift 1 crane vessel was assisted by its heavy transport vessel Mighty Servant 3, which transported a number of jackets from Taipei to the offshore wind farm. 

Boskalis' construction support vessels, BOKA Atlantic and BOKA Tiamat, provided essential supporting activities.Credit: Boskalis    

Offshore Engineer has shared the images above with permission from Boskalis.

Categories: Energy Renewable Energy Industry News Offshore Wind Activity Asia Construction Vessel

Related Stories

DNV Certifies Buchan Floating Offshore Wind Foundation Design

Cadeler Wraps Up Turbine Installation Job at Poland’s First Offshore Wind Farm

Acta Marine Christens Vestas-Chartered CSOV Newbuild

Current News

Shell to Take 30% Stake in Equinor's Bay du Nord Project off Canada

Transocean Adds $1.1B to Offshore Drilling Backlog

Gennaker Offshore Substations Depart for Baltic Sea Installation (Video)

Valeura Starts Wassana Platform Installation Offshore Thailand

Subscribe for OE Digital E‑News