Aker BP Awards Edvard Grieg EPCI Contract to Moreld Apply

OE staff
Friday, January 27, 2023

Engineering firm Moreld Apply said it has been awarded an engineering, procurement, construction and installation (EPCI) contract by Aker BP for the Edvard Grieg topside modification, part of the Utsira High tie-backs project.

The purpose of the contract is to execute the required topside modifications for the Solveig Phase 2, Troldhaugen and Symra tie-back fields to Edvard Grieg in the Norwegian North Sea.

The EPCI contract was an option when Moreld Apply was awarded the front end engineering and design (FEED) contract to plan the modifications in detail in 2022.

The engineering work will start immediately, Moreld Apply said, while the first offshore activities are expected in autumn 2023. The project is estimated to be completed in 2025.

Categories: Engineering Activity Europe Production

Related Stories

SLB to Provide Engineering Services for Norway's Havstjerne CCS Project

BP Completes Central Azeri Platform Maintenance, Ramps Up Production

Aker BP Brings Three Skarv Satellite Fields On Stream

Current News

Northern Territory Shale Developers Look Towards LNG Production

CM Energy to Introduce CM Zenith Offshore Vessel to European Market in 2028

Milei Vows Tougher Sanctions, Defense Push Over Falklands Oil Drilling

ABS to Support Floating Offshore Wind Development in Brazil

Subscribe for OE Digital E‑News