MENCK, Van Oord Partner on Installation of Italy’s First Offshore Wind Farm

Wednesday, April 28, 2021

MENCK has signed a contract with Dutch marine contractor Van Oord to deliver the hammer spread for the installation of the Taranto offshore wind farm, Italy’s first. 

The installation of 10 monopiles, each supporting a 3-MW turbine, will begin in Q3 2021 using the MPI Resolution and is expected to take 16 days. MENCK will supply one MHU 800S hydraulic hammer spread, including service technicians.

The Taranto project is a milestone for offshore wind power in Italy and southern Europe in general. The 30-MW development will be Italy’s first offshore wind farm and the first to be built in the Mediterranean Sea. The project is being run by Italian company Renexia, which is developing other offshore wind projects around the world.

MENCK has previously worked with Van Oord on the Danish Kriegers Flak offshore wind farm, where the companies collaborated to install 72 monopiles in record time.


Image courtesy Menck

Categories: Contracts Offshore Energy Subsea Offshore Wind

Related Stories

ABL Gets Neptun Deep Job for OMV Petrom in Black Sea

TechnipFMC Picks Up ‘Large’ Subsea Contract for ExxonMobil’s Whiptail Off Guyana

Venterra Expands Marine Hard Bottom Benthic Ecology and Hard Structure Services

Current News

Woodside Revenue Falls on Lower LNG, Oil Prices

ABL Gets Neptun Deep Job for OMV Petrom in Black Sea

Petrobras and China’s CNCEC to Collaborate on Oil and Gas, Renewables

Norway Clears TGS and PGS Merger

Subscribe for OE Digital E‑News