Ørsted Fully Commissions 752 MW Borssele 1 & 2 Offshore Wind Farm

Friday, November 27, 2020

Offshore wind developer Ørsted said Friday it had fully commissioned the Borssele 1 & 2 offshore wind farm in the Netherlands.

The wind farm has a capacity of 752 MW, making it the largest offshore wind farm in the Netherlands and the second largest operating offshore wind farm in the world, according to Ørsted.

Borssele 1 & 2, Ørsted's first offshore wind farm in the Netherlands, provides enough electricity to power one million Dutch households.  

Henrik Poulsen, CEO and President of Ørsted, says: "This is an important milestone for the green transformation and for Ørsted. We're proud that we've commissioned our first offshore wind farm in the Netherlands, which is among the global frontrunners in the energy transition. 

With Borssele 1 & 2 as the first step, we wish to make a significant contribution to the Dutch transition from fossil to renewable energy. We're proud that we completed this large-scale clean energy project on time and within budget during the COVID-19 pandemic, while maintaining our focus on health and safety."

Facts about Borssele 1 & 2

Owner: Ørsted
Total capacity: 752 MW
Wind turbines: Siemens Gamesa 8 MW
Size of the site: 112 km2
Number of turbines: 94
Foundation: monopiles
Offshore and onshore grid: TSO TenneT
Operational: Q4 2020
Water depth: 14-36m
Distance to coast: 23 km off the coast of Zeeland
Operation and maintenance base: Vlissingen
Capacity: Can power 1 million Dutch households
Main suppliers: Siemens Gamesa, Sif, Bladt, EEW SPC, EEW OSB, and Nexans
Installation: DEME Offshore, Van Oord

Categories: Activity Europe The Netherlands Offshore Wind

Related Stories

Over 150 Specialist Subsea Jobs Up for Grabs at Rovco and Vaarst

First Turbine Stands Tall at Iberdrola’s 476MW Offshore Wind Farm

Hollandse Kust West Beta Export Cables to Come Ashore Next Week

Current News

Maryland Sets Course for Offshore Wind Energy Expansion

Cadeler Wins Wind Turbine Install Work in the Polish Baltic Sea

Indonesia to Ask Mubadala to Speed Up South Andaman Gas Development

UK’s Offshore Wind Test Facility Gets $100M Overhaul Boost

Subscribe for OE Digital E‑News