Tennet Relocates Submarine Cable from Borssele

Laxman Pai
Wednesday, April 17, 2019

The transmission system operator Tennet has moved the first submarine cable from the Dutch wind farm zone "Borssele" to the transformer station.

"TenneT has laid the first sea cable to connect the Alpha platform to the transformer substation in Borssele. In the morning of Friday 12 April, VBNK started withdrawing the sea cable on land and early Saturday morning the cable reached the newly built transformer substation," said a press release.

The cable-laying vessel, Giant 7, then repositioned itself in the Honte and started with the most critical part of the installation: crossing the fairway.

Before crossing the channel, shipping traffic to and from the port of Antwerp was blocked until Sunday afternoon. The crossing went completely according to plan and the traffic got back on track in the course of the evening.

In the coming weeks, preparations will be made to also connect the second sea cable for the Borssele Alpha project to the transformer station.

Categories: Energy Wind Power Transmission/Gears Subsea Cables

Related Stories

Shell Joins 20 Rivals in Norway's Latest Exploration Round

EnergyPathways Selects Jacobs as Tier-1 Engineering, Regulatory Partner

Chevron, ENI, Geopark Signs Energy Agreements in Venezuela

Current News

Italy Cuts Red Tape to Boost Domestic Oil and Gas Output

SED Energy Holdings and Ventura Offshore Set to Combine Ops

Shell Joins 20 Rivals in Norway's Latest Exploration Round

ExxonMobil Taps Saipem, Jan De Nul for Rovuma LNG Work

Subscribe for OE Digital E‑News