Floating wind project gets go-ahead

OE Staff
Friday, March 17, 2017

Dounreay Trì has been granted planning consent for the installation of a floating windfarm 9km off the Northern Coast of Scotland by the Scottish government.

The decision means that the facility will achieve the necessary Renewables Obligation accreditation by the end of the month to allow it to proceed.

The prototype facility, which will be constructed at Global Energy Group’s Nigg facility in the Highlands, will see a twin turbine project capable of generating 10MW of electricity built and installed.

The next steps for the project is to formally reach a final investment decision. The project needs to be constructed, installed and commissioned by 30 September 2018 under the terms of the Obligation Certification regime. 

Dounreay Trì was created by Swedish design and engineering company Hexicon for the sole purpose of demonstrating Hexicon’s semi-submersible foundation for offshore wind power, off Dounreay, Scotland

The Dounreay Trì Floating Wind Demonstration Project shall consist of:

  • A single semisubmersible platform and two wind turbines with a total capacity of 8-12 MW, about 6km off Dounreay, Scotland; 
  • A single export cable to bring the power to shore; and
  • The associated onshore electrical infrastructure to connect the Project at, or near, the existing substation at Dounreay.

Engineering house Atkins was appointed engineering partner on the project last year.

Categories: Offshore Wind Europe Renewables

Related Stories

Cadeler Lines Up Offshore Wind Foundation Installation Job

RWE Divests Swedish Wind Portfolio in Deal with Nordic Player Aneo

DeepOcean Wraps Up Work at US Offshore Wind Project

Current News

Noble Completes $360M Sale of Five Jack-Ups to Borr Drilling

Russia’s Lukoil Agrees to Sell Foreign Assets to US’ Carlyle Group

Worley Nets Equinor’s Framework Deal for Norway Offshore Assets

Petrobras’ Proven Oil and Gas Reserves Climb to 12.1 Bln Boe

Subscribe for OE Digital E‑News