Elletra installed in Adriatic

Published

The 450-tonne Elettra platform deck sailed away from Rosetti Marino's Piomboni Yard in Marina di Ravenna on July 7, and on Monday 14, the deck was installed in the Adriatic Sea, 33 miles offshore Ancona, Italy.

The scope of work assigned to Rosetti Marino by operator ENI consisted of project management activities, basic and detail engineering, procurement, prefabrication and assembly at yard, mechanical completion, commissioning, load-out, seafastening and transport.

 