BP Moves Indonesia CCUS Project Into Offshore Installation Phase

Friday, July 24, 2026

BP has advanced the Tangguh Ubadari, CCUS and Compression (UCC) project in Indonesia with the first offshore platform jacket arriving in Fakfak, Papua Barat, marking the start of the offshore installation phase.

The jacket completed a 5,800-km journey from the Karimun fabrication yard after more than 357,600 work hours without major incidents, BP said.

The company said the arrival of the approximately 994-tonne structure paves the way for installation activities offshore, with the next phase involving the laying of 75 km of pipeline connecting the platform to the Tangguh LNG facilities.

The Tangguh UCC project comprises development of the Ubadari gas field, onshore compression facilities and a carbon capture, utilizations and storage (CCUS) system. BP said the project is expected to unlock around 3 trillion cubic feet of additional gas resources while incorporating Indonesia's first large-scale CCUS development.

The initial phase of the CCUS project is expected to have the capacity to permanently store about 15 million tonnes of carbon dioxide captured from Tangguh LNG operations.

Tangguh LNG, Indonesia's largest natural gas producer, accounts for around 35% of the country's natural gas production, according to BP.

Categories: FLNG Floating Production Support Vessel Technology LNG Subsea Industry News Activity Asia CCUS Oil and Gas Carbon Capture And Storage

Related Stories

OneSubsea, Oil Majors Complete All-Electric Subsea Technology Project in Brazil

Finder Energy Selects Eneos’ Rig for Drilling Job off Timor-Leste

Vår Energi Makes Gas Discovery in Norwegian Sea

Current News

New Crewsure Energy Program Provides Employee Benefits for Offshore Workers

ABS, Ørsted Tapped for 2026 NOIA Award

Techouse Acquires Ambio

TenneT, NKT Find Offshore Cable Decom Technically Feasible

Subscribe for OE Digital E‑News