Empire Wind Granted Preliminary Injunction, Construction to Resume

Thursday, January 15, 2026

The underlying lawsuit challenging the U.S. Department of the Interior’s December 22, 2025 suspension order will continue to proceed.

Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period. In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.

Empire Wind is being developed under contract with the New York State Energy Research and Development Authority (NYSERDA) to deliver a critical new, near-term source of electricity for New York and bolster grid reliability at a time of rapidly growing demand. Once completed, the project would provide enough power to electrify approximately 500,000 homes in New York.

Categories: Offshore Energy Offshore Energy Industry News Activity U.S. Government US offshore wind Wind Farms

Related Stories

DUG Hooks Multi-Client Seismic Reprocessing Survey off Malaysia

ABL Secures Work at Egypt’s Kamose Gas Field

Island Offshore’s Hybrid OECV Hits Water at Vard Yard in Romania (Video)

Current News

Jifmar, Seavium Partner to Roll Out AI Across Offshore Fleet

DUG Hooks Multi-Client Seismic Reprocessing Survey off Malaysia

ABL Secures Work at Egypt’s Kamose Gas Field

Equinor Hires Havila Shipping’s PSV

Subscribe for OE Digital E‑News