Empire Wind Granted Preliminary Injunction, Construction to Resume

Thursday, January 15, 2026

The underlying lawsuit challenging the U.S. Department of the Interior’s December 22, 2025 suspension order will continue to proceed.

Empire Wind will now focus on safely restarting construction activities that were halted during the suspension period. In addition, the project will continue to engage with the U.S. government to ensure the safe, secure and responsible execution of its operations.

Empire Wind is being developed under contract with the New York State Energy Research and Development Authority (NYSERDA) to deliver a critical new, near-term source of electricity for New York and bolster grid reliability at a time of rapidly growing demand. Once completed, the project would provide enough power to electrify approximately 500,000 homes in New York.

Categories: Offshore Energy Offshore Energy Industry News Activity U.S. Government US offshore wind Wind Farms

Related Stories

IEA: Oil Supply Disruptions to Impact Europe from April

Teledyne eXtreamer for Seismic Data Receives 2026 Spotlight on New Technology Award

Mark Offshore Adds Research Vessel Mintis to Support Offshore Renewables

Current News

DroneQ Robotics, Mark Offshore Collaborate with R/V Mintis

OMV Petrom’s Black Sea Well Fails to Find Significant Gas Volumes

Eco Wave Power Completes Los Angeles Wave Energy Pilot with Shell

Borr Drilling Secures New Drilling Rig Contracts Across Four Regions

Subscribe for OE Digital E‑News