EEW SPC Delivers Last Three Monopiles for Sofia Offshore Wind Farm

Wednesday, June 18, 2025

EEW Special Pipe Constructions (EEW SPC) has loaded out the last three monopiles for RWE’s 1.4 GW Sofia offshore wind farm, being built off the U.K.’s North East coast.

The total of 100 monopiles, with weights of 1,143 to 1,521 tons and lengths of up to 91.8 meters, were loaded onto a barge without incident using the RoRo (roll on/roll off) method with EEW's own SPMTs.

In the meantime, 90 foundations have been transported to the installation site in the North Sea and installed by the transport and installation company Van Oord using the ship Aeolus.

The Sofia wind farm will go into operation in 2026 and will then produce green electricity for around 1.2 million British households.

Currently under construction on Dogger Bank, 195 kilometers from the nearest point on the U.K.’s north east coast, it will comprise 100 Siemens Gamesa 14 MW offshore wind turbines.


Categories: People Renewable Energy Activity Europe Offshore Wind

Related Stories

UK Grants Consent for 1.5GW Outer Dowsing Offshore Wind Farm

Construction Starts on Nederwiek 2 Offshore Wind Grid Platform

Germany’s PNE Loses Bid for Vietnam’s Offshore Wind Project

Current News

Digital Threatscape is Rapidly Evolving for Global Energy Systems

Martens en Van Oord Purchases Autonomous Survey Vessel From Demcon unmanned systems

Mubadala Hires SLB for Deepwater Drilling Services Offshore Indonesia

Cydome Rolls Out Remote Cybersecurity Tool for Offshore Wind Farms

Subscribe for OE Digital E‑News