Greater Tortue Ahmeyim Project Start-Up Could Slide to Q2 2024, Kosmos Energy Says

Reuters
Tuesday, November 7, 2023

Kosmos Energy said on Monday that the start-up of the BP-operated  Greater Tortue Ahmeyim (GTA) gas project offshore Senegal and Mauritania could slip into the second quarter of 2024.

BP last week said that the project was 90% complete and is expected to start production in the first quarter, slightly later than originally planned after BP replaced the contractor for its subsea pipeline system.

The floating production storage and offloading (FPSO) vessel for the GTA project is en route to the field and is expected to arrive in the first quarter of next year, Kosmos said in its third-quarter earnings results.

Kosmos said that the timing of production start-up now depends on the arrival, hook-up, and commissioning of the FPSO as well as the floating liquefied natural gas (FLNG) facility.

"The delivery of first gas in the first quarter of 2024... depends on the execution of this workstream, which has the potential to slip into the second quarter of 2024."

BP declined to comment on Kosmos' update.

BP holds a 56% stake in the GTA project, while Kosmos holds a 26.8% share.

Phase 1 of the project will produce 2.5 million tonnes per year of LNG.

(Reuters - Reporting by Ron Bousso; editing by Jonathan Oatis)


Categories: LNG Industry News Activity FPSO Floating Production Africa FLNG

Related Stories

Finder Energy Buys Petrojarl I FPSO for Timor-Leste Oil and Gas Projects

TotalEnergies, Partners to Plug Financing Gap at $20B Mozambique LNG Project

Eni Starts Up Phase 2 of Congo LNG Ahead of Schedule

Current News

Bloomberg News Reports Shell is Looking for a Buyer for Brazilian Oilfield Cluster

Shell is in advanced discussions to buy LLOG Exploration, say sources. The deal will cost more than $3 billion.

ESG Completes Service Operation Vessel Conversion for HOS

Orbital Marine Power Secures $9.31m Investment

Subscribe for OE Digital E‑News