SK E&S and CIP Seal Deal on 99MW Offshore Wind Project in South Korea

Wednesday, October 11, 2023

SK E&S, one of the largest conglomerates in South Korea, and Copenhagen Infrastructure Partners have reached financial close on the Jeonnam 1 offshore wind project in South Korea.

Jeonnam 1 will be a 99-MW offshore wind farm off the coast of Shinan County, Jeonnam Province in the southwest of Korea. Construction and completion of the wind farm are expected by the end of 2024.

Jeonnam Offshore Wind Power was founded in 2020 as a 51-49 joint venture between SK E&S and Copenhagen Infrastructure Partners (CIP) and the project is expected to become the first Korean commercial-scale offshore wind farm to go into operation in 2024. 

 SK E&S and CIP are also jointly developing Jeonnam 2 and Jeonnam 3, two offshore wind projects with a total capacity of 800MW currently in the development phase. 

"Jeonnam 1, 2 and 3 will support Korea’s ambitious target of reaching 14,3 GW of offshore wind power by 2030, a significant increase compared to the existing 0,1 GW installed today," CIP said Wednesday.

Jeonnam Offshore Wind Power obtained Electricity Business License in 2017 and entered a grid connection agreement with KEPCO, the state-owned utility in South Korea, allowing the project to connect to the grid during 2024. In 2022, Jeonnam I was awarded a 20-year fixed-price offtake agreement with Korea Hydro & Nuclear Power through Korea’s first wind offtake auction.

Throughout 2022, the project also signed manufacturing and construction contracts with Korean suppliers including Hyundai Engineering and Steel Industries, Hyundai Electric and Gaon, KT Submarine and LS Cable and System. The project will utilize Mokpo New Port as marshalling port throughout construction, given the port’s ideal location near the Jeonnam 1 site.

Jeonnam 1 CEO Daniel Yun said, “SK E&S is proud to be leading the offshore wind industry in Korea with this landmark project. Jeonnam 1 is expected to provide green electricity equivalent to approximately 60,000 households in Korea.”

Jeonnam 1 COO Jesper Krarup Holst commented, “We are delighted to reach this milestone and enter the construction phase together with our JV partner and the project team. Together, we have demonstrated the power of close collaboration across companies and cultures to resolve tough challenges, to reach financial close, and to support Korea in its efforts to achieve their ambitious renewable energy goals.”

Torsten Lodberg Smed, senior partner at CIP, said, “Korea has a vast potential for offshore wind and CIP has, since entering the Korean market in 2018, invested significantly in developing the country’s wind power projects in multi-giga watts scale and its supply networks and foster a strong industry ecosystem. We are proud to have reached financial close and entering the construction phase on Jeonnam 1 and we look forward to completing this landmark project together with our partners.

CIP is also pursuing partnerships in Korea regarding the development and supply of blue and green ammonia into Korea to further facilitate Korea’s green transition.”


Categories: Energy Renewable Energy Industry News Activity Asia Renewables Offshore Wind

Related Stories

Asso.subsea Wraps Up Subsea Cables Installation at French Floating Wind Pilot

Second HVDC Platform Installed at World’s Largest Offshore Wind Farm

Deal in Place for 1GW+ Offshore Wind Farm in Southeast Australia

Current News

BP-Eni JV Azule Inks Deal for Namibia Offshore License

NSTA Awards 31 More Licenses in Latest North Sea Oil and Gas Round

Höegh LNG Strikes Deal to Deploy FSRU Hoegh Galleon in Egypt

BW Offshore Concludes Sale of FPSO Polvo

Subscribe for OE Digital E‑News