On November 25, 2020, MV Hawk discharged her final jacket foundation for the Moray East Offshore Wind Farm.

OHT’s heavy transportation vessel carried its second load of 10jackets from Lamprell’s fabrication site in Hamriyah, UAE, arriving at the Port of Nigg in the Cromarty Firth on November 12, 2020, marking the completion of OHT’s eight-month transportation campaign which also used its vessels MV Osprey and MV Albatross. 

All told, OHT transported 48 three-legged jacket foundations averaging more than 1,000 tonnes and up to 80 meters in height.

OHT were contracted by DEME Offshore, the project’s balance of plant EPCI contractor, in September 2019.

"The jacket foundations are amongst the largest in deployment for offshore wind turbines. We are immensely proud to have played a key role in delivering such a critical component for this remarkable offshore wind project," said Egil Ismar, OHT’s Project Manager.


  • Once complete, Moray Offshore Windfarm (East) Ltd (known as ‘Moray East’) will consist of 100 V164 – 9.5MW turbines and will generate sufficient electricity to save 1.4 million tonnes CO₂ equivalent annually.
Categories: Technology Offshore Vessels Offshore Wind

Related Stories

Nam Cheong Sells 3,000 DWT Platform Support Vessel for $19.8m

European North Sea Investment Pact to Mobilize $1.17T for Offshore Wind

James Fisher Backs US Autonomous Vessel Firm Ocean Aero

Current News

France Calls Draft Law on Oil Exploration in Overseas Territories

Formosa 4 Offshore Wind Substation Enters Fabrication Phase

Mozambique and TotalEnergies Restart Stalled $20B LNG Project

Equinor Gets Permit to Drill North Sea Wildcat Well

Subscribe for OE Digital E‑News