Moray East Offshore Wind Farm Jacket Transport Completed

OEDigital
Wednesday, November 25, 2020

On November 25, 2020, MV Hawk discharged her final jacket foundation for the Moray East Offshore Wind Farm.

OHT’s heavy transportation vessel carried its second load of 10jackets from Lamprell’s fabrication site in Hamriyah, UAE, arriving at the Port of Nigg in the Cromarty Firth on November 12, 2020, marking the completion of OHT’s eight-month transportation campaign which also used its vessels MV Osprey and MV Albatross. 

All told, OHT transported 48 three-legged jacket foundations averaging more than 1,000 tonnes and up to 80 meters in height.

OHT were contracted by DEME Offshore, the project’s balance of plant EPCI contractor, in September 2019.

"The jacket foundations are amongst the largest in deployment for offshore wind turbines. We are immensely proud to have played a key role in delivering such a critical component for this remarkable offshore wind project," said Egil Ismar, OHT’s Project Manager.


  • Once complete, Moray Offshore Windfarm (East) Ltd (known as ‘Moray East’) will consist of 100 V164 – 9.5MW turbines and will generate sufficient electricity to save 1.4 million tonnes CO₂ equivalent annually.
Categories: Technology Offshore Vessels Offshore Wind

Related Stories

Kongsberg Maritime Secures LARS Contract with Sea1 Offshore

Seatrium Launches Arbitration Against Maersk Over WTIV Contract Termination

Fugro Wraps Up Survey at Dogger Bank South Offshore Wind Farm

Current News

Dajin Forms Offshore Wind Alliance with German Port Terminal Operator

EnerMech Hires Former SLB Executive to Lead Energy Solutions Division

Eni Expands Asian Footprint with Long-Term LNG Contract in Thailand

Jasmund Substation’s Topside and Jacket Sets Sail to Baltic Sea

Subscribe for OE Digital E‑News