The construction of the 48,000 dwt semi-submersible offshore wind farm foundation installation vessel, Alfa Lift, is progressing at the China Merchants Heavy Industry (CMHI) shipyard.

CMHI has installed 78 out of 162 blocks in the dock of Offshore Heavy Transport’s (OHT) new wind farm foundation installation vessel.

The hull structural steel construction of the remaining blocks is also taking shape; in total 103 of the 162 blocks have reached the non-destructive testing completion status.

Alfa Lift, for which the first steel was cut on 1 March 2019, will be designed to match the future requirements of the offshore wind industry, claimed OHT.

The launching ceremony is planned for March, with Alfa Lift due to be delivered in early 2021.

The design has been developed by OHT in close cooperation with Ulstein Design & Solutions BV, Liebherr and DNV GL.

The vessel has a total length of 216.3m, and a breadth of 56m. It is said to be capable of transporting and installing up to 10 x 1,500 ton jacket foundations or 11 x 2,000 ton monopiles together with transition pieces and mission equipment.

Categories: Shipbuilding Wind Power Offshore Wind Vessles

Related Stories

Jumbo Scoops Two Offshore Wind Contracts

ESG Completes Service Operation Vessel Conversion for HOS

Ocean Winds Hires Seaway7 for Offshore Wind Job in Poland

Current News

BOEM Initiates Process for Potential Mineral Lease Sale Offshore Virginia

Jumbo Scoops Two Offshore Wind Contracts

Wood Nets Long-Term Maintenance Contract for Rio Grande LNG Facility

TechnipFMC to Supply Subsea Systems for Chevron’s Gas Project off Australia

Subscribe for OE Digital E‑News