Nord Stream 2 Pipe Ends Link Underway

Tuesday, August 13, 2019

The Saipem pipelay vessel Castoro 10 (C10) is currently on location offshore Rügen, Germany to tie together the two ends of a Nord Stream 2 pipe string laid last year on the seabed.

The two sections will be connected above water with a weld seam, project operator Nord Stream 2 said on Monday.

In what is known as an Above-Water Tie-In (AWTI) both pipe ends will be lifted out of the water and then cut, aligned and welded together from a working platform attached to the C10. The weld seam is ultrasonically tested and coated with an anti-corrosion protection. Afterwards, the pipe string will be placed on the Baltic seafloor in a slight arc.

Including all preparation and follow-up work, the procedure takes two to three weeks. With optimal weather conditions and smooth operations, the works above water can be completed within just a week.

The C10 is situated northwest of the Landtief approach and positioned with eight anchors. Due to the anchor pattern as well as diving works, a safety distance of at least 1,000 meters from C10 must be observed.

Work on the Nord Stream 2 Pipeline continues to proceed as scheduled. Altogether more than 1,700 kilometers (over 70%) of both pipe strings have been laid in accordance with the existing permits in the waters of Germany, Sweden, Finland and Russia.

Categories: Vessels Engineering Pipelines Pipelay Vessel

Related Stories

Jumbo Scoops Two Offshore Wind Contracts

DEME Set for Monopiles, Cables Installation Job at Polish Offshore Wind Farm

ESG Completes Service Operation Vessel Conversion for HOS

Current News

DeepOcean Awarded IMR Contract Extension by Equinor

BOEM Initiates Process for Potential Mineral Lease Sale Offshore Virginia

Jumbo Scoops Two Offshore Wind Contracts

Wood Nets Long-Term Maintenance Contract for Rio Grande LNG Facility

Subscribe for OE Digital E‑News