Schiehallion Manifold Delivered to BP

Thursday, July 11, 2019

Global Energy Group said its North Fabrication division has completed and handed over the Schiehallion Central Production Manifold M1P to BP.

The 130Te manifold was delivered safely and to the required project quality requirements, the manufacturer said.

OSS awarded Global Energy's North Fabrication division the contract in September 2018, first steel was cut in October 2018 and completed manifold handed over in May 2019.

The manifold will facilitate additional tie-in points for new wells into the Quad 204 (Schiehallion redevelopment) project, a BP spokesperson told OEDigital. The work is progressing on an extended drilling program that has always been part of the project, he said.

Categories: Technology Engineering Subsea Production Hardware

Related Stories

Eco Wave Power Completes Los Angeles Wave Energy Pilot with Shell

Seequent Assesses Offshore Data Today to Prepare for Tomorrow

Cleanova Boosts Seawater Injection Capacity on Gulf of Mexico Platform

Current News

DroneQ Robotics, Mark Offshore Collaborate with R/V Mintis

OMV Petrom’s Black Sea Well Fails to Find Significant Gas Volumes

Eco Wave Power Completes Los Angeles Wave Energy Pilot with Shell

Borr Drilling Secures New Drilling Rig Contracts Across Four Regions

Subscribe for OE Digital E‑News