Schiehallion Manifold Delivered to BP

Thursday, July 11, 2019

Global Energy Group said its North Fabrication division has completed and handed over the Schiehallion Central Production Manifold M1P to BP.

The 130Te manifold was delivered safely and to the required project quality requirements, the manufacturer said.

OSS awarded Global Energy's North Fabrication division the contract in September 2018, first steel was cut in October 2018 and completed manifold handed over in May 2019.

The manifold will facilitate additional tie-in points for new wells into the Quad 204 (Schiehallion redevelopment) project, a BP spokesperson told OEDigital. The work is progressing on an extended drilling program that has always been part of the project, he said.

Categories: Technology Engineering Subsea Production Hardware

Related Stories

Aquaterra’s RAF System for UK CCS Project Enters Fabrication Phase

Eco Wave Power to Explore AI-Driven Wave Energy Optimization

All Systems Go for Technip Energies' Job at Commonwealth LNG Scheme

Current News

Copenhagen Infrastructure Partners Remains Eager to Invest in Italian Offshore Wind

Sercel Nodal Technology Chosen by OGDC for Wireless Seismic Acquisition Project

Weatherford Wins Deepwater Completions Contract off Nigeria

QatarEnergy, ExxonMobil Explore Cyprus Gas Exports via Egypt’s Infrastructure

Subscribe for OE Digital E‑News