InterMoor completes Heidelberg hook-up

InterMoor provided Anadarko Petroleum Corp. with rapid hook-up services for their Heidelberg truss spar in the deepwater Gulf of Mexico after stepping in at short notice for another contractor.

The company hooked up the 80,000 b/d spar to three mooring lines in Green Canyon block 860, offshore Louisiana, at a water depth of 5300ft (1600m). The project’s original contractor then resumed the job and completed the remaining six mooring lines along with the completion of the spar installation.

InterMoor initiated the engineering work in March 2015, began offshore work in early June and completed its part of the hook-up in July.

“Our client required a high level of responsiveness to ensure the project remained on schedule,” said Todd Veselis, manager of projects, InterMoor.

InterMoor mobilized five vessels from Fourchon, Louisiana, and provided crews for each. This involved more than 40 InterMoor staff on two tugs and three anchor-handling vessels. The Kirt Chouest and the Dino Chouest were the main anchor-handling vessels and a third acted as a support vessel between them and the platform. These vessels, as well as McDermott’s DB 50, maintained station keeping for the spar and completed the hook-up operations to get the spar ‘storm safe.’

Previously, InterMoor had fabricated some suction piles for the Heidelberg project in February 2015 and provided representatives during the installation of the Lucius spar, which is identical to the Heidelberg, in 2013.

Image: Heidelberg mooring/ Foster Marketing

Current News

Equinor Upbeat About Investor Interest in US Offshore Wind Farm

Equinor Upbeat About Investor

GE Vernova Could Not Agree Turbines Switch on NY Wind Projects

GE Vernova Could Not Agree Tur

Hess Profit Jumps on Guyana Output in Positive Sign for Exxon

Hess Profit Jumps on Guyana Ou

Decarbonization Offshore O&G: Navigating the Path Forward

Decarbonization Offshore O&G:

Subscribe for OE Digital E‑News

Offshore Engineer Magazine