Production resumes at Tamar

Production has resumed at the Tamar gas field offshore Israel after a crack was found in an emission pipe used to release natural gas and pressure, according to partner Delek Drilling.

Noble was performing upgrade and improvement as planned, when the crack was found in the pipe, which is used routinely and in emergencies. Production was stopped on 21 September.

Today (28 September), Delek says Noble has completed a repair of the fault and production has resumed. Noble is continuing to carry out other planned upgrade works, says Delek. 

The Tamar field is in License 309 in the Matan Block, about 90km west of Haifa in the Levantine Basin. 

Noble Energy Mediterranean is the operator of the Tamar project with 32.5% stake. Partners include:  Isramco Negev 2 (28.75%), Delek Drilling (22%), Tamar Petroleum( 9.25%), Dor Gas Exploration (4%), and Everest Infrastructures (3.5%).

Read more:

Malfunction stops production at Tamar

Current News

US Offshore Wind: Outlook Strong Despite Construction Productivity Issues

US Offshore Wind: Outlook Stro

Bourbon Orders Exail Tech to Streamline Subsea Fleet’s Services for Offshore Energy

Bourbon Orders Exail Tech to S

Asso.subsea Wraps Up Subsea Cables Installation at French Floating Wind Pilot

Asso.subsea Wraps Up Subsea Ca

Dayrates Rise - Will More Energy Companies Buy Offshore Rigs?

Dayrates Rise - Will More Ener

Subscribe for OE Digital E‑News

Offshore Engineer Magazine