Assuring the future of FLNG

The engineering challenges posed by colossal FLNG projects are in danger of dwarfing the practicalities of realizing the build. That needn’t be the case. Focusing on the vendor equipment supply chain from the outset, and the choice of codes and standards employed, are critical areas where expenditure can be protected, risks can be reduced and asset life can be enhanced. Get these strategies right and we will see a growing number of mega-projects over the next decade.

Mark Tipping.

Supply chains have always been critical to industry’s success. Traditional shipbuilding supply chains, for example, have been developed – perfected even – to allow yards to construct ships as effectively as possible. The supply chain remains equally as important for FLNG assets; the issue is that it is not ships being built, but a new breed of floating unit. Almost every parameter has changed.

While some of the world’s largest yards are able to stretch to accommodate these vast units, elements of the equipment supply chain are coming under enormous strain. There are a few reasons for this. Much of the technology being applied to FLNG assets is novel, revolutionary even when it comes to the liquefaction of natural gas on a moving platform. This has led to a steep leaning curve for equipment suppliers, many of whom have not been exposed to the floating offshore environment before. To this, add the sheer scale and pace of FLNG projects. The result is that even relatively straightforward orders, such as for process pipework, need to be shared among as many as 15 separate suppliers, who must all meet the same high-quality expectations. This is a real challenge because, beneath seemingly standard requests, lie unforeseen complications. ‘Standard’ implies repeatability, consistency and predictability of outcome, but standards applied to FLNG equipment are often blended and synthesized, and therein lies the risk. To the equipment vendor, what looked like an order on paper for a forged-steel, heavy-duty API 600 valve turns out to be not quite that item in practice. The situation is compounded by another factor: a wider supply chain than ever before. Whereas shipbuilding is production-centered, with the major part of the supply chain within a 100km radius of the yard, FLNG construction is engineering-based. In place of shipbuilding’s steady trade, there are short runs. Instead of predictability and repeatable expectations, there are bespoke standards and novel demands. Now a finely honed production system is relying on a supply chain 20,000km or so in radius, opening up the project to uncertainty and risk, both technically and commercially.

Operating in a whole new area, there is much to lose. Costing up to $13 billion each, FLNG projects are vast when compared to the very largest commercial shipping orders. As a ballpark figure, and give or take 10% or so either way, topside manufacture accounts for half of an FLNG vessel’s total build sum, with a further 25% invested in the hull. The remaining budget is split between cargo containment (2.5%), accommodation (2.5%) and other systems and components (20%). If new build costs spiral, particularly in core parts, the very future of the FLNG business will be in jeopardy. To date, it has been FLNG’s engineering challenges that have attracted attention and resources, from designing super-large hulls to adapting major plant liquefaction systems for floating installations, preventing sloshing, safeguarding against cryogenic spills and devising other innovative solutions. This is more than understandable. But now, with advances made, there is everything to gain by rethinking the approach to the vendor equipment supply chain, one of the biggest risks to an FLNG project’s success. Despite the issues raised, there are a number of opportunities to improve the experience, reduce risks and realize potential costs savings. Here, Lloyd’s Register points to two critical factors.

First, there is the choice of codes and standards to be made. Should an owner opt for the vendors’ benchmark – typically an industry standard, such as ASME, AWS, IEC or Class – or their own proprietary requirements? This decision is rightly seen as a matter of risk versus cost, but it needs broader consideration. By setting its own standards, a company can reassure stakeholders of the very best project intentions, and satisfy the demands set by legal and supply-chain specialists. However, this approach will be expensive, arguably prohibitively so for such vast FLNG projects. Vendors will charge a premium for delivering equipment to tailored specifications and owners will need to check that their specifications are being met. This is a global task, across a supply chain that will span some 25 countries, or more if we factor in sub-suppliers. Critically, will best intentions deliver the required equipment, systems and components to the yard? It is early days for FLNG, but supply chains are already being challenged. It is not hard to picture a worrying emerging pattern where initial standards are diluted, equipment is sourced from outside of approved vendor lists and a project’s progress is stalled as suppliers realize that the specifications go beyond what was envisaged. Inevitably, new build costs will escalate, along with a heightened risk that supply chain issues will become operational problems. To all of this, there is another compelling argument for rethinking the codes and standards applied to FLNG projects. Currently, FLNG new builds adopt the traditional approach for offshore projects, that is applying marine standards to every component below the main deck (except the accommodation) and internationally recognized petrochemical standards to the topsides and process equipment. This approach is not fit for purpose. On FLNG assets, marine, topside and processing equipment are more greatly integrated than has previously been the case, with some marine equipment migrating into the topsides and, conversely, certain topsides components moving down into the hull. Drawing an arbitrary line along the main deck and applying codes and standards according to the break isn’t a cost-effective answer to realizing the most from the supply chain, especially when considering the challenges it faces. Nor does it provide the safest option.

The solution is to review both the marine and petrochemical standards based on process requirements and safety considerations, assigning equipment, components and systems to either the marine or offshore process according to best engineering and safety practices, rather than where the deck begins. At Lloyd’s Register, we have formalized this task into a ‘Classification Plan’, part of our organization’s ‘Offshore Rules’. This initiative brings together over 50 years of offshore experience, including our technical knowledge of LNG containment and liquefaction technology, FPSO development and process engineering systems. Besides better delineation of codes and standards, the approach offers a means for owners to identify their critical asset equipment and rate it accordingly. This is the first method of cost saving that can be employed with no risk to a project, provided safety remains a constant driver.

By taking this approach further, we can also help owners find the optimum balance between risk and cost, driving international requirements where they need to be driven, challenging others where safety and reliability can be assured, establishing bespoke specifications only when they need to be special, and taking advantage of universal codes and standards where items are of a routine nature or fit and compatibility can be guaranteed. The complexity of FLNG projects will never lend itself to a blanket approach here, but the fewer bespoke specifications, the greater the opportunity to reduce risk and cost with equipment supply,since unfamiliar requirements are not being imposed on vendors and the danger of these requirements being missed altogether is eliminated. Acting as early on in a project as possible is fundamental. Involving technical experts such as our organization at the Concept/FEED stage will deliver the greatest support in selecting the most appropriate codes and standards and de-risking the project.

With codes and standards clear, supply chain assurance will be the second factor in delivering successful FLNG projects. As a leading provider of compliance and validation services, we know the value to major projects of ensuring that there is no weak link in the supply chain. With the right strategies and processes in place, owners will have a stronger safety net in halting increasing new build costs. Getting to this advantageous position can only begin by understanding the new nature of the FLNG supply chain, accepting it, and adapting to it accordingly.

Given that everything is new, a change in mindset is required. Greater engagement with the supply chain will prove central, at least to the level of the sub-supplier. Owners and contractors will need to understand their suppliers’ position, as much as suppliers must immerse themselves in the project’s vision. Vendors must known what non-compliance looks like, with project-specific requirements being singled out in the procurement specification document. Enhanced management across the chain is also vital. Given the sheer extent of equipment vendors, owners must budget, and plan for, an extensive coordination effort. At key locations, informed, dedicated teams acting as expeditors, certifiers and consultants will prove invaluable, critically reviewing and revising reporting formats and mechanisms to focus on problems (project matters), rather than defects (local matters). Regular, timely communication will also help, with provision for handling feedback and enquiries from the supply chain, as well as broadcasting instructions. Enhanced management will mean monitoring every link in the chain – from specification to tendering, award, pre-production and delivery – and acting swiftly to address early signals of potential issues. You get what you actively manage, not pay for, should be the FLNG project mantra.

Cost savings and reduced risks aside, focusing efforts now on the FLNG vendor supply chain offers a couple of other compelling benefits. Getting the right equipment in place will ultimately contribute to the longevity of an asset. Or put another way, supply chain issues are only temporary; on a 40-year project, all problems come back to the owner or operator. This focus will also contribute to developing a much-needed third type of specialist, one who bridges the gap between marine and topside equipment. Employing people who are not just qualified but experienced in the standards and procedures applicable to FLNG projects will help make this innovative technology revolutionary in the natural gas business. 

Mark Tipping is Principal Engineer – FLNG Development at Lloyd’s Register as well as class engineering project manager on the Prelude project. He has been with Lloyd’s Register since 2012, before which he was ABS Europe as senior engineer, also covering FLNG. He studied Mechanical Engineering at the University of Portsmouth.

Current News

Strohm Reels In ExxonMobil’s Third TCP Deal Offshore Guyana

Strohm Reels In ExxonMobil’s T

Ocean Charger for Offshore Wind Vessels Proves a Success

Ocean Charger for Offshore Win

Allseas Makes Progress on Santos’ Barossa Gas Export Pipeline in Australia

Allseas Makes Progress on Sant

HSM Rolls Out Topside for ONE-Dyas’ Offshore Wind-Powered Gas Platform

HSM Rolls Out Topside for ONE-

Subscribe for OE Digital E‑News

Offshore Engineer Magazine